Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
20 Cards in this Set
- Front
- Back
What DON instruction establishes the policy regarding Operational Risk Management (ORM)?
|
OPNAV Instruction 3500.39B
|
|
Who is responsible for operational risk management, and when?
|
All individuals are responsible for operational risk management, on and off duty.
|
|
When should ORM be applied?
|
All naval activities shall apply the ORM process in planning, operations and training to optimize operational capability and readiness.
|
|
The concept behind ORM is?
|
a) A decision making tool used by personnel at all levels to increase operational effectivemess by identifying, assessing, and managing risks. By reducing the potential for loss, the probably of a successful mission is increased.
b) Increase our ability to make informed decisions by providing a formal operational risk management process. c) Minimize risk to acceptable levels. The amount of risk accepted at war is more than peace, but the process remains the same. |
|
Identify the first step in ORM:
|
Identify hazards
*Begin with an outline or chart of the major steps in operation (operational analysis). Conduct a Preliminary Hazard Analysis by listing all of the hazards associated with each step in the operational analysis along with possible causes for those hazards. |
|
Identify the second step in ORM:
|
Assess Hazards
*For each hazard identified, determine the associated degree of risk in terms of probability and severity. Although not required, the use of a matrix may be helpful in assessing harzards. |
|
Identify the third step in ORM:
|
Make Risk Decisions
*First, develop risk control options. Start with the most serious risk first and select control that will reduce the risk to a minimum consistent with mission accomplishment. Decide if the benefit outweighs the risk. If risk outweighs benefit, consult with the chain of command. |
|
Identify the fifth step in ORM:
|
Supervise
*Conduct follow-up evaluations of controls to ensure they remain in place and have the desired effect. Monitor for changes, which may require further ORM. |
|
What is a Category I hazard?
|
CAT I: The hazard may cause death, loss of facility/asset or result in grave damage to national interests.
|
|
What is a Category II hazard?
|
CAT II: The hazard may cause severe injury, illness, or property damage, damage to national or service interests or degradation to efficent use of assets
|
|
What is a catagory III hazard?
|
Cat III: The hazard may cause minor injury, illness, property damage, damage to national, service or command interests or degradation to efficient use of assets.
|
|
What is a catagory IV hazard?
|
Cat IV: The hazard presents a minimal threat to personnel safety or health property, national, service or command interests of efficient use of assets.
|
|
What is Mishap Propability?
|
The probability that a hazard will result in a mishap or loss, based on an assessment of various factors.
|
|
What is mishap probability Sub-catagory A?
|
Sub-catagory: Likely to occur immediately or within a short period of time. Expected to occur frequently to an individual item or person or continuously to a fleet, inventory or group.
|
|
What is mishap probability sub-catagory B?
|
Sub-catagory B: Probability will occur in time. Expected to occur several times to an individual item or person or frequently to a fleet, inventory or group.
|
|
What is mishap probability sub-catagory C?
|
Sub-catagory C: May occur in time. Can reasonably be expected to occur some time to an individual item or person or several times to a fleet, inventory or group.
|
|
What is mishap probability sub-catagory D?
|
Sub-catagory D: Unlikely to occur.
|
|
Identify the fourth step in ORM:
|
Implement Controls
*Use the following measures to eleminate hazards or reduce the degree of risk (listed by preference: 1. Engineering Controls 2. Aministrative Controls 3. Peronal Protective Equipment |
|
What are the three ORM process levels?
|
1. Time Critical
2. Deliberate 3. In depth *Deciding which of the three levels is necessary is based on the situation, proficiency level, and time and assets available. |
|
The Risk Assessment Code (RAC) uses numbers within a severity matrix to indicate risk. Define the numbers.
|
RAC Definitions:
1 - Critical risk 2 - Serious risk 3 - Moderate risk 4 - Minor risk 5 - Negligible risk |