How many processes in "Project Time Management"
|
6
Define Activities Sequence activities Estimate Activity Resources Estimate ACtivity Durations Develop Schedule Control Schedule |
Project Time Management
|
|
What is the process of time management?
|
Define activities
Sequence activities Estimate activity resources Estimate activity durations Develop schedule Control schedule |
Project Time Management
|
|
In which process is the schedule management plan created?
|
The schedule management plan is created in the integration management process as part of develop project management plan
|
Project Time Management
|
|
What are key outputs of the define activities process?
|
Activity list
Activity attributes Milestone list |
Project Time Management
|
|
What a key outputs of the sequence activities process?
|
Network diagrams
Project document Updates |
Project Time Management
|
|
What is a key output of the estimate activity resources process?
|
Activity resource requirements
|
Project Time Management
|
|
What are key outputs of the control schedule process?
|
Work performance measurements
Change requests Updates To Project Management Plan And Project Documents |
Project Time Management
|
|
Question:
efine Activities Process Group |
Answer:
• Planning |
Project Time Management
|
|
Question:
Define Activities Knowledge Area |
Answer:
• Project Time Management |
Project Time Management
|
|
Question:
Define Activities Inputs |
Answer:
• Scope baseline • Enterprise environmental factors • OPA |
Project Time Management
|
|
Question:
Define Activities Tools & Techniques |
Answer:
• Decomposition • Rolling wave planning • Templates • Expert judgement |
Project Time Management
|
|
Question:
Define Activities Outputs |
Answer:
• Activity list • Activity attributes • Milestone list |
Project Time Management
|
|
Question:
Sequence Activities Process Group |
Answer:
• Planning |
Project Time Management
|
|
Question:
Sequence Activities Knowledge Area |
Answer:
• Project time management |
Project Time Management
|
|
Question:
Sequence Activities Inputs |
Answer:
• Activity list • Activity attributes • Milestone list • Project scope statement • OPA |
Project Time Management
|
|
Question:
Sequence Activities Tools & Techniques |
Answer:
• Precedence diagraming method (PDM) • Dependency determination • Applying leads & lags • Schedule network templates |
Project Time Management
|
|
Question:
Sequence Activities Outputs |
Answer:
• Project schedule network diagrams • Project document updates |
Project Time Management
|
|
Question:
Estimate Activity Resources Process Group |
Answer:
• Planning |
Project Time Management
|
|
Question:
Estimate Activity Resources Knowledge Area |
Answer:
• Project Time Management |
Project Time Management
|
|
Question:
Estimate Activity Resources Inputs |
Answer:
• Activity list • Activity attributres • Resource calendars • Enterprise environmental factors (EEF) • OPA |
Project Time Management
|
|
Question:
Estimate Activity Resources Tools & Techniques |
Answer:
• Expert judgement • Alternatives analysis • Published estimating data • Bottom up estimating • PM software |
Project Time Management
|
|
Question:
Estimate Activity Resources Outputs |
Answer:
• Activity resource requirements • Resource breakdown structure • Project document updates |
Project Time Management
|
|
Question:
Estimate Activity Durations Process Group |
Answer:
• Planning |
Project Time Management
|
|
Question:
Estimate Activity Durations Knowledge Area |
Answer:
• Project time management |
Project Time Management
|
|
Question:
Estimate Activity Durations Inputs |
Answer:
• Activity list • Activity attributes • Activity resource requirements • Resource calendars • Project scope statement • EEF • OPA |
Project Time Management
|
|
Question:
Estimate Activity Durations Tools & Techniques |
Answer:
• Expert judgement • Analogous estimating • Parametric estimating • 3 point estimates • Reserve analysis |
Project Time Management
|
|
Question:
Estimate Activity Durations Outputs |
Answer:
• Activity duration estimates • Project document updates |
Project Time Management
|
|
Question:
Develop Schedule Process Group |
Answer:
• Planning |
Project Time Management
|
|
Question:
Develop Schedule Knowledge Area |
Answer:
• Project time management |
Project Time Management
|
|
Question:
Develop Schedule Inputs |
Answer:
• Activity list • Activity attributes • Project schedule network diagrams • Activity resource requirements • Resource calendars • Activity duration estimates • PSS • EEF • OPA |
Project Time Management
|
|
Question:
Develop Schedule Tools & Techniques |
Answer:
• Schedule network analysis • Critical path method • Critical chain method • Resource leveling • What if scenario analysis • Applying leads & lags • Schedule compression • Scheduling tool |
Project Time Management
|
|
Question:
Develop Schedule Outputs |
Answer:
• Project schedule • Schedule baseline • Schedule data • Project document updates |
Project Time Management
|
|
Question:
Control Schedule Process Group |
Answer:
• Monitoring & controlling |
Project Time Management
|
|
Question:
Control Schedule Knowledge Area |
Answer:
• Project Time Management |
Project Time Management
|
|
Question:
Control Schedule Inputs |
Answer:
• PMP, Project Management Plan • Project schedule • Work performance information • OPA, Organizational Process Assets |
Project Time Management
|
|
Question:
Control Schedule Tools & Techniques |
Answer:
• Performance reviews • Variance analysis • PM software • Resource leveling • What if scenario analysis • Adjusting leads & lags • Schedule compression • Scheduling tool |
Project Time Management
|
|
Question:
Control Schedule Outputs |
Answer:
• Work performance measurements • OPA updates • Change requests • PMP updates • Project document updates |