Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
120 Cards in this Set
- Front
- Back
Role of project sponsor during project initiation is to assist in:
-Defining projects objectives in both business and technical terms -Developing the project plan -Performing the project feasibility analysis -Performing project cost-benefit analysis |
Defining projects objectives in both business and technical terms
|
|
Role of project sponsor during project execution:
-Validate project's objectives -Validate execution of plan -Make all project decisions -Resolve problems/conflicts that can’t be resolved elsewhere in the organization |
Resolve problems/conflicts that can’t be resolved elsewhere in the organization
|
|
Role of the project sponsor during the closure of the project or a life-cycle phase of the project is to:
-Validate that profit margins are correct -Sign off on acceptance of deliverables -Administer performance reviews of project team members -All of the above |
Sign off on acceptance of the deliverables
|
|
Document that officially sanctions a project:
-Project charter -Project plan -Feasibility study -Cost benefit analysis |
Project charter
|
|
Work breakdown structure control points for the management of a project:
-Milestones -Work packages -Activities -Constraints |
Work packages
|
|
One of most common reasons projects undergo scope changes:
-Poor work breakdown structure -Poorly defined statement of work -Lack of resources -Lack of funding |
Poorly defined statement of work
|
|
Cannot be validated using a work breakdown structure:
-Schedule control -Cost control -Quality control -Risk management |
Quality control
|
|
Performance measurement baseline is most often composed of three baselines:
-Cost, schedule, risk -Cost, schedule, scope -Cost, risk, quality -Schedule, risk, quality |
Schedule, cost, scope
|
|
Benefits of developing WBS to low levels:
-Better estimation of costs -Better control -Less likely for things to fall through cracks -All of the above |
All: Better estimation of costs, better control, less likely for things to fall through cracks
|
|
Baselines, once established, identify:
-What the customer and contractor agree to -What the sponsor and customer agree to -What the customer wants done but not necessarily what the project manager plans to do -What the project manager plans to do, not necessarily what the customer has asked for. |
What the project manager plans to do, not necessarily what the customer has asked for.
|
|
Financial closeout is used to:
-Close out all charge numbers -Close out all charge numbers for work performed and completed -Amend work authorization forms -None |
Close out all charge numbers for work performed and completed
|
|
Contractor asking to conduct only eight tests rather than 10 tests required by spec. PM first action should be:
-Change scope baseline -Ask contractor to initiate a change request -Look at penalty clauses in contract -Ask sponsor |
Ask contractor to initiate a change request
|
|
Contractor sends email to use high quality raw materials to be value added and improve quality. PM should:
-Change scope baseline -Ask contractor to initiate a change request -Ask sponsor -Change WBS |
Ask contractor to initiate a change request
|
|
Maximum number of subsidiary plans a program management plan can contain:
-10 -15 -20 -Unlimited |
Unlimited
|
|
Change control board approves significant scope change. First document PM should update would be:
-Scope baseline -Schedule -WBS -Budget |
Scope baseline
|
|
Shortest time necessary to complete all activities in a network is called:
-Activity duration length -Critical path -Maximum slack path -Compression path |
Critical path
|
|
Cannot be identified after forward and backward pass:
-Dummy activities -Slack time -Critical path activities -How much OT is planned |
How much OT is planned
|
|
Not a commonly used technique for schedule compression:
-Resource reduction -Reducing scope -Fast tracking activities -Use of OT |
Resource reduction
|
|
Disadvantage of using bar charts to manage a project
-Do not show dependencies between activities -Ineffective for projects under one year -Are ineffective for projects under $1 million -Do not identify start and end dates of schedule |
Do not show dependencies between activities
|
|
Reducing peaks and valleys in manpower assignments to obtain relatively smooth manpower curve:
-Manpower allocation -Manpower leveling -Resource allocation -Resource commitment planning |
Manpower leveling
|
|
Activities with no time duration:
-Reserve activities -Dummy activities -Zero slack activities -Supervision activities |
Dummy activities
|
|
Optimistic, pessimistic and most likely times are associated with:
-PERT -GERT -PDM -ADM |
PERT
|
|
Most common “constraint” or relationship in precedence network is:
-Start-to-start -Start-to-finish -Finish-to-start -Finish-to-finish |
Finish-to-start
|
|
Network based technique that allows for branching and looping:
-PERT -GERT -PDM -ADM |
GERT
|
|
If activity on critical path takes longer than anticipated:
-Activities not on the critical path have additional slack -Activities not on the critical path have less slack -Additional critical path activities will appear |
Activities not on critical path have additional slack.
|
|
Which of the following is a valid way of obtaining proper project performance information?
-First hand observations -Oral and written reports -Review and technical interchange meetings -All of the above |
All:
-First hand observations -Oral and written reports -Review and technical interchange meetings |
|
Proper graphical display of information can result in:
-Reducing paperwork costs -Reducing reporting costs -Reduce time for routine decisions -All of the above |
All:
-Reducing paperwork costs -Reducing reporting costs -Reduce time for routine decisions |
|
Which is a valid way to evaluate financial feasibility of a project?
-Return on investment -Net present value -Internal rate of return -All |
All:
-Return on investment -Net present value -Internal rate of return |
|
3 common classification systems for estimates include all except:
-Parametric estimates -Quick and dirty estimates -Analogy estimates -Engineering estimates |
Quick and dirty estimates
|
|
Most accurate estimates are:
-Parametric estimates -Quick and dirty estimates -Analogy estimates -Engineering estimates |
Engineering estimates
|
|
Which is a bottom-up estimate rather than a top-down estimate?
-Parametric estimates -Analogy estimates -Engineering estimates -None |
Engineering estimates
|
|
Which would be considered as a cost-estimating relationship (CER)?
-Math equations based on regression analysis -Learning curves -Cost-cost or cost-quality relationships -All |
All:
-Math equations based on regression analysis -Learning curves -Cost-cost or cost-quality relationships |
|
If a worker earns $30/hr in salary, but project is charged $75/hr for every hour they work; overhead rate is:
-100% -150% -250% -None |
150%
|
|
Information supplied to a customer to support financial data provided in a proposal is:
-Backup data -Engineering support data -Labor justification estimates -Legal rights estimates |
Backup data
|
|
Estimating pitfalls can result from:
-Poorly defined SOW -Failure to account for risks in estimates -Using wrong estimating techniques -All |
All:
-Poorly defined SOW -Failure to account for risks in estimates -Using wrong estimating techniques |
|
Source of many estimating risks is:
-Poorly defined requirements -Inexperienced PM -Lack of management support during estimating -All |
All:
-Poorly defined requirements -Inexperienced PM -Lack of management support during estimating |
|
Project where scope evolves as work takes place is called either progressive planning or:
-Synchronous planning -Continuous planning -Rolling wave planning -Continuous reestimation planning |
Rolling wave planning
|
|
Calculation of the total cost of product, from R&D to operational support and disposal, is called:
-Birth to death costing -Life cycle costing -Summary costing -Depreciation costing |
Life cycle costing
|
|
In earned value measurement, earned value is represented by:
-BCWS -BCWP -ACWP -None |
BCWP
|
|
If BCWS = 1000, BCWP = 1200, ACWP = 1300, the project is:
-Ahead of schedule, under budget -Ahead of schedule, over budget -Behind schedule, over budget -Behind schedule, under budget |
Ahead of schedule, over budget
|
|
If BAC = 20K and project is 40% complete, earned value is:
-5K -8K -20K -Cannot determine |
8K
|
|
If BAC = 12K and CPI=1.2, variance at completion is:
-(2K) -2K -(3K) -3K |
BCWP/ACWP = 1.2
12/x=1.2 1.2x=12 12/1.2 = 10k = ACWP +2k |
|
If BAC = 12K and CPI = .8, variance at completion is:
-(2K) -2K -(3K) -3K |
BAC/BCWP = 12k
CPI = .8 = BCWP - ACWP .8 = 12k-ACWP .8ACWP = 12k 12k/.8 = 15k -3K |
|
If BAC for a work package is 10k and BCWP = 4K, work package is:
-40% complete -80% complete -100% complete -120% complete |
40% complete
|
|
If CPI= 1.1 and SPI = .95, then the trend for the project is:
-Running over budget, ahead of schedule -Running over budget, behind schedule -Running under budget, ahead of schedule -Running under budget, behind schedule |
Running under budget, behind schedule
|
|
Document that describes a work package, identifies cost centers allowed to charge against it, and establishes the charge number is:
-Code of accounts -Work breakdown structure -Work authorization form -None |
Work authorization form
|
|
Unknown problems such as escalation factors are often budgeted for using:
-PM charge number -Project sponsor charge number -Management reserve -Configuration management cost account |
Management reserve
|
|
EAC, ETC, SPI, CPI most often appear in which report?
-Performance -Status -Forecast -Exception |
Forecast
|
|
If BAC=24K, BCWP =12K, ACWP = 10K, CPI = 1.2, cost that remains to finish project is:
-10k -12k -14k -Cannot determine |
10k
|
|
Several purposes for 50/50 rule, but primary purpose is to calculate:
-BCWS -BCWP -ACWP -BAC |
BCWP
|
|
When a project is completed, which must be true?
-BAC=ACWP -ACWP=BCWP -SV=0 -BAC = ETC |
SV=0
|
|
In March CV = (20K), April CV = (30K). To tell whether situation has deteriorated because of larger unfavorable cost variance, need to calculate:
-CV in % -SV in $ -SV in % -All |
SV in %
|
|
If PM is looking for revenue from value added scope change, first choice would be:
-Management reserve -Customer funded scope change -Undistributed budget -Retained profits |
Customer funded scope change
|
|
Project was originally scheduled for 20 months. If CPI is 1.25, then the new schedule date is:
-16 months -20 months -25 months -Cannot determine |
Cannot determine
|
|
The cost or financial baseline of a project is composed of:
-Distributed budget only -Distributed and undistributed budgets only -Distributed budget, undistributed budget & management reserve only -Distributed budget, undistributed budget & management reserve and profit only |
Distributed budget, undistributed budget only
|
|
BUDGETED COST FOR WORKED SCHEDULED (BCWS)
|
Budgeted amount of cost for work scheduled to be accomplished + amount of level of effort scheduled in a given time period
*Subtracted to find schedule variance *PV *How much of the work should be done? |
|
BUDGETED COST FOR WORK PERFORMED (BCWP)
|
Budgeted amount of cost for completed work, + budgeted for level of effort activity in a given time period
*Earned value *Point of comparison for cost and schedule variance =% complete * BAC *How much of the work is done? |
|
ACTUAL COST FOR WORK PERFORMED (ACWP)
|
Amount reported as actually expended in completing work accomplished in a given time period.
*Subtracted to find cost variance *Actual cost *How much did the "is done" work cost? |
|
COST VARIANCE
|
CV =BCWP - ACWP
*Compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished. *Negative variance = cost overrun *Measures efficiency: to correct, emphasize productivity (burn rate) at which work is being performed |
|
SCHEDULE/PERFORMANCE VARIANCE
|
SV = BCWP - BCWS
*Provides a comparison between planned and actual performance but does not include costs. *Negative variance = behind schedule *To correct, emphasize speed at which work is being performed |
|
SCHEDULE VARIANCE % = (SVP)
|
(SV/BCWS) * 100
|
|
COST VARIANCE % = (CVP)
|
(CV/BCWP) * 100
|
|
Estimate at completion (EAC)
|
EAC = (ACWP/BCWP) * BAC (Budget at completion)
The estimate at completion is the best estimate of the total cost at the completion of the project. *What do we now expect the total job to cost? The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified. |
|
CPI (cost performance index)
|
BCWP/ACWP
*If <1, unfavorable (being accomplished at higher cost than planned) |
|
SPI (schedule performance index)
|
BCWP/BCWS
*If <1, unfavorable (being accomplished at slower rate than planned) |
|
BAC - budget at completion/total budget
|
What was the total job supposed to cost?
|
|
Variance at completion
|
VAC = BAC - EAC
VAC = BAC - [(ACWP/BCWP)*BAC] |
|
Tradeoffs are almost always necessary because:
-PMs are incapable of planning correctly -Line managers are unable to provide accurate estimates -Executives are unable to properly define project objectives -Circumstances can change, thus mandating tradeoffs take place |
Circumstances can change, thus mandating tradeoffs take place
|
|
The person who may ultimately be responsible for approving tradeoffs is:
-Project manager -Line manager -Project sponsor -Customer |
Customer
|
|
Most common tradeoffs occur over:
-Time, cost, quality -Risk, cost, quality -Risk, time, quality -Scope, quality, risk |
Time, cost, quality
|
|
If start date of project is delayed but budget and specs are fixed, what would the project manager trade off first?
|
Quality
|
|
The two components of risk are:
|
Uncertainty and impact
|
|
Risk management is normally performed by
|
Developing contingency plans
|
|
Future outcomes that provide favorable opportunities are called:
|
Opportunities
|
|
The cause of a risk event is usually referred to as:
|
A hazard
|
|
If there's a 40% chance of making 100k and 60% chance of losing 150k, the expected monetary outcome is:
|
-50000
|
|
Assumption, mitigation and transfer are examples of risk:
|
Responses
|
|
In which life cycle phase would project uncertainty be the greatest?
|
Initiation
|
|
In which life cycle phase would financial risks of a project be the greatest?
|
Closure
|
|
Identifying a risk as high, moderate, or low would be an example of which risk assessment?
|
Qualitative
|
|
Monte Carlo simulation is an example of which risk assessment?
|
Quantitative
|
|
Which of the following is not a valid reason for managing a risk?
|
Providing a late as possible warning system
|
|
Which of the following is generally not part of overall risk management?
|
Selecting the PM
|
|
A technique for risk evaluation that uses a questionnaire, series of rounds, and reports submitted in confidence and then circulated with the source unidentified is called:
|
The Delphi Technique
|
|
Risk symptoms or early warning signs are called
|
Triggers
|
|
Which of the following is not a risk quantification tool or technique?
|
Objective setting
|
|
A technique that depicts interactions among decisions and associated events is called:
|
Decision tree analysis
|
|
Varying one risk driver at a time, either in small increments or from optimistic to pessimistic estimates while keeping all other drivers fixed, is called:
|
Sensitivity analysis
|
|
A risk response strategy that generally reduces the probability or impact of the event without altering the project's objectives is called:
|
Mitigation
|
|
Earned value measurement is an example of:
|
Risk monitoring and control
|
|
The difference between being proactive and reactive is the development of a:
|
Contingency plan
|
|
According to learning curve theory, learning takes place at a fixed rate whenever the production levels
|
Double
|
|
Learning curve theory is most appropriate for estimating which costs?
|
Manufacturing
|
|
On a 90% learning curve, the 100th unit required 80 hours. How many hours would the 200th unit require?
*** |
Shouldn't this be 72? Book says 90. How can it increase? Check.
|
|
Which of the following can be a source of improvement to a learning curve?
|
All of the above
|
|
The contractual statement of work is
|
A narrative description of the work deliverables to be accomplished and/or the resource skills required
|
|
A written or pictorial document that describes, defines, or specifies the services or items to be procured is
|
A specification document
|
|
The order of precedence is
|
The document that specifies the order/priority in which project documents will be used when it becomes necessary to resolve inconsistencies between project documents
|
|
In which type of contract arrangement is the contractor least likely to want to control costs?
|
Cost plus percentage of cost
|
|
In which type of contract arrangement is the contractor most likely to want to control costs?
|
Firm fixed price
|
|
In which type of contract arrangement is the contractor at the most risk of absorbing all cost overruns?
|
Firm fixed price
|
|
In which type of contract arrangement is the customer at the most risk of absorbing all cost overruns?
|
Cost plus percentage of cost
|
|
What is the primary objective the customer's project manager focuses on when selecting a contract type?
|
Creating reasonable contractor risk with provisions for efficient and economical performance incentives for the contractor
|
|
Which type of contract arrangement is specifically designed to give a contractor relief for inflation or material/labor cost increases on a long term contract?
|
Firm fixed price with economic price adjustment
|
|
Which of the following is not a factor to consider when selecting a contract type?
|
Type/complexity of requirement, urgency of requirement and price competition extent are all factors to consider
|
|
In a fixed price incentive fee contractor, the point of total assumption refers to the point in the project cost curve where:
|
The contractor assumes responsibility for every additional dollar that is spent in fulfilling the contract
|
|
A written preliminary contractual instrument prepared prior to the issuance of a definitive contract that authorizes the contractor to begin work immediately, within certain limitations, is a
|
Letter contract/letter of intent
|
|
A contract entered into after following normal procedures, e.g. negotiation of terms, conditions, cost and schedule, but prior to initiation of performance is known as a
|
Definitive contract
|
|
Which of the following is not a function of contract admin activity?
|
Selecting the PM
|
|
A fixed price contract is typically sought by the PM from the customer org when
|
The risk and consequence associated with the contracted task are large and the customer wants to transfer the risk
|
|
Which of the following are typical actions a customer would take if the customer received nonconforming materials or products and the customer didn't have the ability to bring goods into conformance?
|
Accept the shipment on the condition that the nonconforming products will be brought into conformance by the vendor at the vendor's expense
|
|
If a PM requires use of a piece of equipment, what is the breakeven point where leasing and renting are the same?
|
100 days
|
|
In which type of incentive contract is there a maximum or minimum value established on the profits allowed for the contract?
|
Cost plus incentive fee contract
|
|
In which type of incentive contract is there a maximum or minimum value established on the final price for the contract?
|
Fixed price incentive fee contract
|
|
A cost plus incentive fee contract has the following characteristics:
Sharing ratio 80/20 Target cost 100k Target fee 12k Max fee 14k Min fee 9k How much will the contract be reimbursed if cost of performing work is 95k? |
Cost - 95K
Fee - 12K 20% of 5K savings under target cost - 1K 108K total |
|
A cost plus incentive fee contract has the following characteristics:
Sharing ratio 80/20 Target cost 100k Target fee 12k Max fee 14k Min fee 9k How much will the contractor be reimbursed if the cost of performing the work is 85K? |
Cost - 85K
Fee - 12K 20% of 15K savings under target cost, up to max total fee of 14K: 2K 99K |
|
A cost plus incentive fee contract has the following characteristics:
Sharing ratio 80/20 Target cost 100k Target fee 12k Max fee 14k Min fee 9k How much will the contractor be reimbursed if the cost of performing the work is 120K? |
120k cost
Fee - 12K Minus customer savings for being over cost, up to min fee of 9K: (3K) 129K 132K |
|
A fixed price incentive fee contract:
Sharing ratio 70/30 Target cost 100k Target fee 8K Price ceiling 110k How much will contractor be reimbursed if cost of performing the work is 90k? |
Target Cost 100k
Actual Cost 90k Savings - 10k Contractor Share - 10k (30%) = 3k Fee = 8K 101k |
|
A fixed price incentive fee contract:
Sharing ratio 70/30 Target cost 100k Target fee 8K Price ceiling 110k How much will contractor be reimbursed if cost of performing the work is 102k? |
Target cost 100k
Actual Cost 102k Overrun - 2k Contractor Deduction = $600 102k+8K-600 =109,400 |
|
A fixed price incentive fee contract:
Sharing ratio 70/30 Target cost 100k Target fee 8K Price ceiling 110k How much will contractor be reimbursed if cost of performing the work is 105k? |
Actual Cost 105K
Fee 8K Overrun 5K Contractor deduction =1500 Revised Fee 6,500 105K+6.5K = 111.5K - exceeds ceiling Pay 110K |