BAC =
(Budget at completion) |
SUM of PV (Planned value) at project completion
|
|
EV=
(Earned Value) |
% COMPLETE * BAC or PV
(Budget at Complete) (Present Value) |
|
CV=
(Cost Value) |
EV-AC
(>0 good) (Earned Value) (Actual Costs) |
|
SV =
(Schedule Variance) |
EV-PV
(>0 good) (Earned Value) (Planned Value) |
|
CPI =
(Cost Performance Index) |
EV/AC
(>1 good) (Earned Value) (Actual Costs) |
|
SPI =
(Schedule Performance Index) |
EV/PV
(>1 good) (Earned Value) (Planned Value) |
|
EAC =
(Estimate at completion) |
AC/ % COMPLETE
-or- BAC/Cum. CPI -or- AC + bottom-up ETC |
|
ETC
(Estimate to Complete) |
EAC-AC
(Estimate at completion - Actual Cost) |
|
VAC
(Variance at Completion) |
BAC-EAC
(Budget at Completion - Estimate at Completion) |
|
TCPI
|
(BAC-EV) / (BAC-AC)
-or- (BAC-EV) / (EAC-AC) Remaining work / Remaining Budget |
|
AC =
(Actual Cost) |
CV / (CPI-1)
(Cost Variance) (Cost Performance Index) |
|
PV =
(Planned Value) |
SV / (SPI-1)
|
|
PTA =
|
( (Ceiling Price - Target Price) / Buyer's Share Ratio)) + Target Cost
|
|
EMV =
(Expected Monetary Value) |
Impact * Probability
|
|
FIND COMMUNICATION CHANNELS
|
N (N-1)
---------- 2 (n = number of people) |
|
COST TO BUY =
|
Initial cost + # of months * monthly maintenance costs
|
|
NORMAL DISTRIBUTION
(6 sigma formulas) |
1 sigma = 68.26%
2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.999% 1 SD = 1 Sigma |
|
PV =
(Present Value) |
FV
---------- (1 + r)n (FV = Future Value; r=rate of interest) (n = number of time periods |
|
PERT =
(Program Evaluation and Review Technique) |
(O+4M+P)/6
(Optimistic) (Most Likely) (Pessimistic) |
|
Present Value =
|
FV / (1 + r)n
FV = Future Value; r = rate of interest n=number of time periods |
|
Variance of Activity =
|
[SD] squared
|
|
Float =
|
LS - ES = LF-EF
(Late Start - Early Start = Late Finish - Early Finish) |
|
Forward Pass =
|
EF = ES + Duration
(Early Finish) (Early Start) |
|
Backward Pass =
|
LF = LS + Duration
(Late Finish) (Late Start) |
|
FLOAT =
|
Float = LS - ES
Float = LF - EF (Late Start) (Early Start) (Late Finish) (Early Finish) |