Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
40 Cards in this Set
- Front
- Back
- 3rd side (hint)
What are the five process groups?
|
Initiating (2), Planning, Executing (20), Monitoring and Controlling (8), and Closing (2)
|
|
|
#1
|
Develop Project Charter
|
Project Integration Management
Initiating Process Group |
|
#2
|
Identify Stakeholders
|
Project Communications Management
Initiating Process Group |
|
#3
|
Develop Project Management Plan
|
Project Integration Management
Planning Process Group |
|
#4
|
Collect Requirements
|
Project Scope Management
Planning Process Group |
|
#5
|
Define Scope
|
Project Scope Management
Planning Process Group |
|
#6
|
Create WBS
|
Project Scope Management
Planning Process Group |
|
#7
|
Define Activities
|
Project Time Management
Planning Process Group |
|
#8
|
Sequence Activities
|
Project Time Management
Planning Process Group |
|
#9
|
Estimate Activity Resources
|
Project Time Management
Planning Process Group |
|
#10
|
Estimate Activity Durations
|
Project Time Management
Planning Process Group |
|
#11
|
Develop Schedule
|
Project Time Management
Planning Process Group |
|
#12
|
Estimate Costs
|
Project Cost Management
Planning Process Group |
|
#13
|
Determine Budget
|
Project Cost Management
Planning Process Group |
|
#14
|
Plan Quality
|
Project Quality Management
Planning Process Group |
|
#15
|
Develop Human Resources Plan
|
Project Human Resources Management
Planning Process Group |
|
#16
|
Plan Communications
|
Project Communications Management
Planning Process Group |
|
#17
|
Plan Risk Management
|
Project Risk Management
Planning Process Group |
|
#18
|
Identify Risks
|
Project Risk Management
Planning Process Group |
|
#19
|
Perform Qualitative Risk Management
|
Project Risk Management
Planning Process Group |
|
#20
|
Perform Quantitative Risk Management
|
Project Risk Management
Planning Process Group |
|
#21
|
Plan Risk Management
|
Project Risk Management
Planning Process Group |
|
#22
|
Plan Procurements
|
Project Procurement Management
Planning Process Group |
|
#23
|
Direct and Manage Project Execution
|
Project Integration Management
Executing Process Group |
|
#24
|
Perform Quality Assurance
|
Project Quality Management
Executing Process Group |
|
#25
|
Acquire Project Team
|
Project Human Resource Management
Executing Process Group |
|
#26
|
Develop Project Team
|
Project Human Resource Management
Executing Process Group |
|
#27
|
Manage Project Team
|
Project Human Resource Management
Executing Process Group |
|
#28
|
Distribute Information
|
Project Communications Management
Executing Process Group |
|
#29
|
Manage Stakeholders Expectations
|
Project Communications Management
Executing Process Group |
|
#30
|
Conduct Procurements
|
Project Procurement Management
Executing Process Group |
|
#31
|
Monitor and Control Project Work
|
Project Integration Management
Monitoring and Controlling Process Group |
|
#32
|
Perform Integrated Change Control
|
Project Integration Management
Monitoring and Controlling Process Group |
|
#33
|
Verify Scope
|
Project Scope Management
Monitoring and Controlling Process Group |
|
#34
|
Control Scope
|
Project Scope Management
Monitoring and Controlling Process Group |
|
#35
|
Control Schedule
|
Project Time Management
Monitoring and Controlling Process Group |
|
#36
|
Control Costs
|
Project Cost Management
Monitoring and Controlling Process Group |
|
#37
|
Perform Quality Control
|
Project Quality Management
Monitoring and Controlling Process Group |
|
#38
|
Report Performance
|
Project Communications Management
Monitoring and Controlling Process Group |
|
#39
|
Monitor and Control Risks
|
Project Risk Management
Monitoring and Controlling Process Group |