• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/21

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

21 Cards in this Set

  • Front
  • Back

In each diary kept by the owner/engineer, entries should be made:

To document every working day, whether any work is performed or not, or even if you did not go to the project site that day. If a dispute arises in the field between the owner/engineer the contractors superintendent, the party shirt:

If a dispute arises in the field between the owner/engineers and the contractors superintendent, the party should:

Move the discussion to a location in the field office, then listen to the dispute, protest, or claim. Then the party should discuss the issues calmly and rationally, even in the face of serious disagreement.

When testing and sampling materials for a project, the owner/engineer or inspector should do which of the following:

Develop a sampling and testing plan in advance and working directly from it.

In order to remember important project dates, it is desirable to:

Tabulate and flag project milestones at the beginning of the job

Submittal of bonds and insurance certificates should be submitted by the bed or to whom the contract has been awarded after receiving notice of award, but before honor signs the agreement

After receiving notice of award, but before owner signs the agreement.

When construction materials are delivered to the project site, they should be:

Inspected as soon as after delivery as possible

Carefully documented project records should be kept in the form of:

Daily construction progress reports and daily diaries.

If there is a conflict between the various parts of contract documents, which of the following would generally prevail?

Specifications.

On our construction work where the owner/engineer has signed an inspector to inspect the work, then Spector should do which of the following:

Inspect the work during construction and notify the contractor of any non-conforming items of work as soon as they’re discovered.

In the daily handling of problems during the relationships between the contractor and the owner the resident project representative should do which of the following:

Listen to the contractor side of each problem or protest; then discuss the matter amicably and reach a judgment reflecting a cooperate of attitude.

If a discrepancy is discovered which makes literal interpretation of the plans and specifications impossible, the owner/engineers or inspector should:

Telephone the project manager engineer responsible for the plans and specifications for instructions before proceeding with the work.

When the owner/engineers inspector or resident project representative or the contractors superintendent leave the project site for a while, it is permissible to do which of the following:

Notify the office of your absence and leave a number where you can be reached.

When I small changes to be made in the field which will result in a departure from the original plans and specifications, the owner/engineers resident project representative or inspector should do which of the following

Issue a change order or work directive change for each such change.

For public works project, changes may not be made to any document doing which of the following phases?

After bid opening, but before signing of the agreement.

If you are working for the owner/engineer and you are called upon in the field to make an important decision in the field you should:

Study the matter long enough to investigate all of the fax their impact on other portions of the work, then return to the contractor with the decision.

If you are working for the owner/engineer and you are called upon in the field to make an important decision in the field you should:

Study the matter long enough to investigate all of the fax their impact on other portions of the work, then return to the contractor with the decision.

At the beginning of a project, they careful study should be made of:

The plant is best of occasions including the “front-end” documents.

Take all the information from the collar, then advise him or her to bid the job as it was originally specified unless an addenda is

Take all the information from the collar, then advise him or her to bid the job as it was originally specified unless an addenda is Issued, and that if an error was in fact discovered, it will be corrected by addenda which will be mailed to all bidders.

Photograph should be taken on the project site:

Regularly, showing our principal features, problems, and progress made to date.

The relationship of the owner/engineers or inspector to the contractor should be which of the following:

A firm but I amiable and cordial member of the construction team.

If you are employed by the owner or engineer and you observe a safety hazard that could result in serious injury or death of a worker, (an imminent hazard) you should do which of the following:

Order the workers that are in potential danger to remove themselves from the hazardous area, then take administrative action to have the contractor correct the situation.