• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/15

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

15 Cards in this Set

  • Front
  • Back

What is the maximum installation volume (IV) that can be worked on as per IGE/UP/1b 2nd Ed?




i 0.025m3


ii 0.035m3


iii 0.02m3


iv 0.02m3

A. 0.035m3

What is the installation volume of an e6 gas meter?




i 0.008m3


ii 0.025m3


iii 0.0036 m 3


iv 0.0024m3

A. 0.0024m3




(G4/U6 meter is 0.008)

When calculating the volume of pipework what allowance is made for fittings?




i 0.5m3 for each elbow/ tee


ii 10%


iii 50%


iv 0.1 m3 for each elbow/ tee

A. 10%

What is the IV of the installation specified below?




g4 meter


6 meters x 22mm copper pipe




i 0.002 112m3


ii 0.008 352m3


iii 0.009 92m3


iv 0.010 112m3

A. (IVmeter + IVpipe+ IVfittings [10%])




0.010 112m3

What is the IV of the installation specified below?




U16 meter


15 metres x 32mm steel pipe




i 0.0261m3


ii 0.04150m3


iii 0.04315m3


iv 0.04815m3







A. (IVmeter + IVpipe+ IVfittings [10%])




=0.04315m3

When conducting a let by test and the water within the gauge rises by more than 0.25mbar what procedure should you follow


i The test would be stopped and the gas supplier would be called to repair.


ii Move straight onto tightness test as suspected let by would have no detrimental effect on the test


iii Connect a temporary bonding across the meter then disconnect the ecv and spray LDF into the barrel to prove you have let by


iv Disconnect the ECV and spray LDF into the barrel to prove you have let by.

A. Connect a temporary bonding across the meter then disconnect the ecv and spray LDF into the barrel to prove you have let by

After completing a successful pressure tightness test, there is still a possibility that the regulator may have locked up, what must now be done to ensure that the installation is tight?


i Re-test the installation at 15mb


ii This will not happen if the correct test pressure used


iii Carry out an air test on the whole installation


iv LDF ECV/AECV outlet and regulator connections



A. LDF ECV/AECV outlet and regulator connections



What type of gas meter requires extra care when performing a test for tightness?


i Quantum gas meter


ii Coin operated gas meter


iii Medium pressure gas meter


iv Ultrasonic meter

A. Quantum gas meter

What is maximum pressure drop allowed for an existing system with a g4 metre and 35mm Pipework, there is no smell of gas and meter installation pipework is tight?


i 4mbar


ii 0mbar


iii 8 mbar


iv 2.5mbar



What is the purge volume of the installation specified below?IVp is 0.00588m3Gas meter is U1628 mm pipework

If you were called to a gas leak and it was tight but there was still a smell of gas when ECV was turned off, what procedure would you follow?


i Advise the responsible person the test has passed and then relight appliances


ii Call CORGI to notify that the system was tight but there is still a smell of gas


iii If smell can not be eliminated call Emergency service provider


iv Ventilate premises when smell clears installation may now be used

A. If smell can not be eliminated call Emergency service provider

What would be the tightness test pressure and tightness test duration when conducting a tightness test of an installation where the pressure in the service is in the medium pressure range and no MIV fitted?




i 19mbar and 2 mins


ii 10mbar and 2 mins


iii 0 mbar and 1 minute


iv 20mbar and 1 minute



A. 19mbar and 2 mins

What is the purge volume of the installation specified below?

(IVm +IVp+IVf x 1.5)

What is the purge volume of the installation specified below?

(IVm +IVp+IVf x 1.5)

What purging procedure must be employed when the installation contains a U16 meter?




i Purge through an unprotected burner without lighting the gas


ii Purge through an unprotected burner and continually attempt to light the gas


iii Either of the above methods at the engineer's decision


iv Purge through a loosened fitting without igniting the gas

A. Purge through an unprotected burner and continually attempt to light the gas

What is the maximum volume in relation to purging in accordance with IGE/UP/1B2nd ed?




i Maximum PV of 0.02m3


ii Maximum IV of 0.0035m3


iii at the engineer's discretion


iv No limit

A. Maximum IV of 0.0035m3